How much does it cost to build a house in Pakistan in 2026? Here are realistic per-square-foot rates for grey structure and turnkey construction — and exactly what makes the number go up or down.
Grey structure vs turnkey — the two numbers that matter
Construction cost is always quoted per square foot of covered area. There are two headline rates: the grey structure rate (the bare, un-finished building) and the turnkey / finishing rate (a move-in-ready home). Confusing the two is the number-one reason people underestimate their budget.
| Package | 2026 rate (per sq ft) | What it includes |
|---|---|---|
| Grey structure | Rs 2,000 – 3,800 | Foundation, RCC frame, blockwork, plaster, conduiting |
| Turnkey (standard finish) | Rs 5,000 – 6,500 | Grey structure + tiling, paint, woodwork, fixtures |
| Turnkey (premium finish) | Rs 6,500 – 9,000+ | Imported tiles, designer kitchen, premium fittings |
Rates vary by area — DHA and the F/E sectors sit at the top of the band, B-17 and the airport-side societies at the bottom. See the full 2026 rate table by area, or use our construction cost calculator for an instant estimate on your covered area.
2026 rates by area (Islamabad)
| Area | Grey structure | Turnkey |
|---|---|---|
| DHA Islamabad | Rs 2,500 – 3,700 | Rs 6,000 – 8,800 |
| Islamabad F & E sectors | Rs 2,600 – 3,800 | Rs 6,200 – 9,000 |
| Bahria Town / Bahria Enclave | Rs 2,300 – 3,300 | Rs 5,600 – 8,200 |
| Gulberg / Park View | Rs 2,300 – 3,400 | Rs 5,600 – 8,400 |
| Islamabad G & I sectors | Rs 2,200 – 3,100 | Rs 5,300 – 7,600 |
| B-17 / Top City / Mumtaz City | Rs 2,000 – 2,900 | Rs 5,000 – 7,300 |
Don't forget the extensions: basement & pool
A basement is not priced at your normal rate — shoring, dewatering, RCC retaining walls and multi-layer waterproofing push it to Rs 3,200 – 4,500 / sq ft. A swimming pool runs Rs 4,500 – 7,000 / sq ft of pool (a standard 20×10 ft pool ≈ 200 sq ft) including shell, filtration and tiling. Both are add-ons in our cost calculator.
What decides where you sit in the range
- Steel and cement prices — the biggest swing factor, and they change monthly.
- Design complexity — basements, large spans, curved work and heavy elevations cost more.
- Finish level — local vs imported tiles, standard vs designer kitchen, simple vs layered ceilings.
- Covered area — larger homes get slightly better per-foot efficiency.
- Site conditions — soil, water table and access affect foundation cost.
How to budget accurately
Calculate your covered area (all floors), pick grey or turnkey, and multiply by the right rate. Add 8–12% contingency for price movement. Then get a real, itemised quote — our grey structure and turnkey contracts fix the rate so your budget doesn't drift.